Limited Time Discount Offer
30% Off - Ends in 02:00:00

X

CompTIA PK0-003 Dumps

CompTIA
CompTIA Project+
CompTIA
CompTIA Project+

Questions & Answers for CompTIA PK0-003

Showing 1-15 of 298 Questions

Question #1 - Topic 1

Which of the following has occurred when project costs are baselined?

A. The project manager has determined when they will need to make purchases

B. The project costs have been spent

C. The business has approved the budget

D. The estimated costs of the project are fixed

Question #2 - Topic 1

Which of the following conflict resolution techniques results in mutual agreement among
conflicting parties?

A. Forcing

B. Avoiding

C. Smoothing

D. Compromise

Question #3 - Topic 1

The project manager is reviewing the earned value of work completed compared to the
planned value and is representing it in a dollar figure. This type of analysis is an example of
which of the following?

A. Cost performance index

B. Risk mitigation

C. Schedule variance

D. Cost variance

Question #4 - Topic 1

Which of the following communication methods would be used to update the project
steering committee?

A. Daily phone conferences outlining key activities

B. A monthly financial and project summary report

C. A daily email highlighting the project spend

D. A standup meeting with the entire project team

Question #5 - Topic 1

Which of the following components of the project charter is used to help determine the
projects communication needs?

A. Stakeholder identification

B. Project objectives

C. Problem statement

D. Key deliverables

Question #6 - Topic 1

Which of the following represents a good reason for formally closing out a project?

A. To provide historical information for future projects

B. To manage stakeholders’ expectations

C. To promote team cohesiveness

D. To keep a record in case someone comes back later with an issue after transition

Question #7 - Topic 1

An email to end users regarding the go-live of an upcoming software release is an example
of:

A. interactive method.

B. push method.

C. formal method.

D. pull method.

Question #8 - Topic 1

Which of the following inputs are used in quality control? (Select TWO).

A. Quality metrics

B. Quality reviews

C. Quality checklists

D. Quality corrective actions

E. Quality change request

Question #9 - Topic 1

Which of the following would use the WBS to aid in the creation of the cost estimate?

A. Analogous

B. Top down

C. Parametric

D. Bottom up

Question #10 - Topic 1

The stakeholder has notified the project manager that new priorities have caused them to
shift all of the business subject matter expert resources to a new project for one year. The
BEST course of action for the project manager is:

A. phase gate review.

B. project cancellation.

C. project completion.

D. stage completion.

Question #11 - Topic 1

Which of the following is the purpose of a post mortem analysis?

A. Determines the degree of accuracy of activity duration estimates

B. Compares the initial project baselines to end of project baselines

C. Highlights detected quality issues and the resolution to the issues

D. Documents the reasons for an early project closure

Question #12 - Topic 1

Which of the following can aid in the identification of the cause of the majority of the defects
on a given project?

A. Ishikawa diagrams

B. Run charts

C. Histograms

D. Pareto charts

Question #13 - Topic 1

A company is replacing their file server with a new one. During the data migration, the old
file server experiences critical hardware failure. The data migration cannot continue until
the hardware is replaced. This repair will put the project behind schedule by a week. Which
of the following actions should the project manager do FIRST?

A. Prepare performance report

B. Manage the issue

C. Schedule a meeting

D. Update communication plan

Question #14 - Topic 1

One of the development resources on a project team does not agree with how quality
assurance testing is being executed. Which of the following should the project manager
do?

A. Schedule a risk assessment meeting

B. Prepare performance reports

C. Start executing additional testing

D. Review the quality management plan

Question #15 - Topic 1

In month nine of a 12-month project, the customer approaches the project manager
believing the project is at risk because 85% of the funds have been expended already. To
give the customer a more accurate assessment, the project manager calculates the Cost
Variance (CV) using which of the following formulas?

A. CV = PV – AC

B. CV = AC – EV

C. CV = EV – PV

D. CV = EV – AC

×